WELCOMEStatus of Hydropower Projects Under Construction in Marshyangdi Corridor in respect to Power Evacuation – Lamjung Kathmandu 8 Dec 2017 Contents • Marsyangdi Corridor Projects • Each Projects Status • Existing 132kV System • Marsyangdi Corridor T/L & Status • Dordi Corridor T/L and SS Status • Connection and Conclusion 00 April. 2019 Power Partner Construction HPPL .00 PPA (Processing) Phase PHPCL Under Peoples Hydro Super Dordi HEP-Kha 54.00 December.00 Aug. 2020 Construction NHL Development Peoples Hydro Himchuli Dordi HEP 57.2022 Construction NG Under Nyadi Hydro Ltd Nyadi HP 30. Projects in Marshyangdi Corridor Capacity Projects RCoD Status Company (MW) Under Nyadi Group Super Nyadi HPP 40. 2019 Construction (LEDCO) Himalayan Under Dordi HEP 27. 2019 LECL Construction Under DJCL Dordi-I HEP 12.27 July.00 July. 2020 Construction PHPCL Under Liberty Energy Upper Dordi-A HEP 25.00 Aug. 00 MW) 132 kV. (Marshyangdi Corridor) . Pictorial View of Marshyangdi/Dordi Corridor To Manang. (Marshyangdi Corridor) Super Nyadi HP (40. 12 km (Dordi Corridor) Dordi HP (27 MW) Udipur S/S (132 kV/220 kV) 220 kV (Marshyangdi Corridor) To Marki Chowk.27 MW) Nyadi HP (30 MW) Himchuli Dordi HP (57 MW) Tadikuna Khudi S/S (220 kV) Super Dordi HP-Kha (54 MW) Upper Dordi-A HEP (25 MW) Kirtipur S/S (132 kV) 220 kV (Marshyangdi Corridor) Dordi-I HEP (12. Project Status . 2022 132 kV Transmission Line Design Ongoing Interconnection Point Tadikuna Sub-Station Length (Switchyard to Tadikuna Sub-Station) 11 km Route Survey Completed Land identification along T/L route and Commenced procurement Process of T/L IEE Started to prepare TOR Completion Target Within July.27 MW). 2022 Overall Project Status Under Construction .Super Nyadi HP (40. T/L Status (NG) Particular Present Status Overall Project Completion 6% RCoD July. 2020 132 kV Transmission Line Design Completed Interconnection Point Tadikuna Sub-Station Length (Switchyard to TadiKuna Sub-Station) 6 km Route Survey Completed Land identification along T/L route and Completed procurement Process of T/L IEE Tender in Jan 2018 Completion Target March.Nyadi HP (30 MW). T/L Status (NHL) Particular Present Status Overall Project Completion 30% RCoD April. 2020 Overall Project Status Under Construction . 2020 Overall Project Status Under Construction .Kha (54 MW). T/L Status (PHPCL) Particular Present Status Overall Project Completion 25% RCoD July. 2020 132 kV Transmission Line Design Completed Interconnection Point Kirtipur Sub-Station Length (Switchyard to Kirtipur Sub-Station) 5.June.2 km Route Survey Completed Land identification along T/L route and Commenced procurement Under process (ToR submitted Process of T/L IEE to DoED for approval) Completion Target Within .Super Dordi HEP . 2019 132 kV Transmission Line Design Completed Interconnection Point Kirtipur Sub-Station Length (Switchyard to Kritipur Sub- 0 km Station) Route Survey Completed Land identification along T/L route and Completed procurement Process of T/L IEE Under process Project Completion Target Dec.Upper Dordi .A HEP (25 MW). 2018 . T/L Status (Liberty) Particular Present Status Overall Project Completion 60% RCoD Aug. I HEP (12.Dordi . T/L Status (DJCL) LEDCO Particular Present Status RCoD December 2019 Interconnection Point Kirtipur Sub-Station Completion Target December 2019 Overall Project Status Under Construction .0 MW). Dordi HEP (27 MW). T/L Status (HPPL) Particular Present Status Overall Project Completion 60% RCoD Aug. 2019 132 kV Transmission Line Design Completed Interconnection Point Udipur Sub-Station Length (Switchyard to Udipur Sub- 1. 2018 .2 km Station) Route Survey Completed Land identification along T/L route and Completed procurement Process of T/L IEE Under process Project Completion Target Dec. Pictorial View of the Existing 132 kV TL Tadikuna Khudi S/S Kathmandu 132 kV S/S 132 kV S/S Marshyangdi HP 132 kV Middle 132 kV S/S Marshyangdi HP 132 kV 132 kV 132 kV S/S Bharatpur Damauli 220 kV S/S Pokhara 132 kV S/S 132 kV S/S . Marshyandgi Corridor Status . Pictorial View of the Marshyagdi & Dordi Corridor TL Dordi Corridor Marshyangdi Kirtipur S/S Corridor 132 kV S/S To Maang 220 kV 132 kV Tadikuna Khudi S/S Markin Chowk 220 kV S/S 220 kV S/S 220 kV 220 kV Udipur S/S 220 kV 132/220 kV S/S Bharatpur 220 kV S/S . Udipur S/S (132 kV/220 kV). TadiKunna S/S (220 kV).Marshyangdi Corridor 220 kV TL connects Manang. Marking Chock S/S (220 kV) to Bharatpur/Kathmandu T/L Line . Udipur Tadikuna To Udipur Transmission 2. 220 kV (Double Circuit) Line Udipur To Markin chowk 3. 85 km long Transmission Line 6. 36 km long Transmission Line Marking Chowk To Bharatpur 4. Overall Status (Line) Tendering process . 220 kV (Double Circuit).N Particular Details/Status 1. 220 kV (Double Circuit). Proposed Sub-station (NEA) Tadikuna Khudi. Marshyangdi Corridor T/L S. Transmission Line Marki Chowk To Kathmandu 5. 220 kV (Double Circuit). Tadikuna Sub-Station Status (220 kV) Particular Status Location Tadikuna Khudi. Sub-Station Land Identification and Land Land Acquired Acquisition Sub-Station Construction EIA in process . Sub-Station Land Identification and Land Land Acquired Acquisition . Udipur Sub-Station Status (132 kV/220kV) Particular Status Location Udipur. Dordi Corridor Status . Dordi Corridor T/L connects Kirtipur S/S (132 kV) to Udipur S/S (132kV/220kV) (12 km long) . 12 km long Transmission Line -Land Obtained By NEA 3. Dordi Rural 1.N Particular Status Proposed Sub-station Kirtipur Besi. (NEA) Municipality Lamjung District Kirtipur To Udipur 2. 132 kV (Double Circuit). Udipur Sub-Station -132 kV/220 kV . Dordi Corridor T/L S. Dordi Rural Location Municipality (Nearby Upper Dordi-A HEP Switch Yard) Sub-Station Land Identification and Completed Land Acquisition Sub-Station Tendering Stage Construction . Kritipur Sub-Station Status Particular Status Kirtipur Besi. Kirtipur to Udipur T/L Status Particular Status Survey License Obtained by NEA Survey Work Completed IEE Completed Land Acquisition Under Process Overall Status Tendering Stage . 2019 No A HEP months (December (17 months Energy loss) (July 2019) 2020) Dirdi-I HEP Dec.2022 NA HP (6 months Energy loss) NA Yes Nyadi HP April. 2020 (9 Months Energy Loss) Expected Expected to Super Dordi to No complete Yes July 2020 (6 months Energy loss) Hp-Kha complete within 3 Upper Dordi – within 20 years Yes Aug. 2019 No Yes (17 months Energy loss) . 2019 No Yes (13 months Energy loss) Dordi HEP Aug. Conclusion Grid Connection possibility as per present situation Dordi Corridor Marshyangdi Corridor Projects RCoD (Kirtipur to Udipur S/S) (Manang to Udipur) Completio Impact Completion Impact n Target Target Super Nyadi Yes July. THANK YOU Any Questions? .
Report "TRANSMISSION LINE STATUS Dordi-Marshyandgi-Dordi Corridor "