Thermal EngineeringGEA EGI Contracting/Engineering Co. Ltd. LIST OF REFERENCES HELLER System: Indirect Dry and Dry/Wet Cooling Systems Page | 1 GEA EGI Contracting/Engineering Co. Ltd. Budapest, Hungary www.egi.hu preheating. 16 150 000 1962 Natural draft. Hungary 100 290 000 1969 Natural draft. recirculation. preheating. Bilibino Nuclear Power Station. Kanegafuchi Chemical Works Japan 60 110 000 1974 Mechanical draft. recirculation. Great Isfahan Power Station. with louvres 120 500 000 1962 Natural draft Decommissioned in 1994 5. Unit II. Unit I. Razdan Power Station. green house heating 24. Russia 12 120 000 1972 Mechanical draft . recirculation. Dunaújváros Steel Mill Hungary 3. Unit IV. Unit V. surface condenser 19. deluged dry tower 22.hu . Armenia 210 580 000 1974 Repeat order. with louvres and DC heater 15. Ltd. with louvres and DC heater 16. Unit No. 1 6. Pilot plant Hungary 0. Armenia 210 580 000 1971 Natural draft steel tower with louvres 13. see Nos. UK 4. 10 through 12 21. Budapest. with louvres and DC heater 10. green house heating 25. with movable shutter 7. Unit I. Ibbenbüren Power Station Germany 150 450 000 1967 Natural draft. recirculation. Mátra (Gagarin) Power Station. Unit V. Unit II. Mátra (Gagarin) Power Station Hungary — 4 000 1983 LOTHUS system. surface condenser 17. Bilibino Nuclear Power Station. Russia 12 120 000 1972 Mechanical draft . Unit III. Hungary www. preheating. Unit II. Flötzersteig Incinerator Austria 3 20 000 1970 Natural draft 14. Mátra (Gagarin) Power Station. Russia 60 80 000 1978 Deluged dry tower with louvres 23. 2 Kazakhstan 6 40 000 1968 Mechanical draft. surface condense 20. Razdan Power Station. Unit IV.8 10 000 1954 Mechanical draft 2. Rugeley Power Station. with movable shutter Karaganda Steel Mill. surface condenser 18. Unit IV. Ivanovo Power Station. Russia 12 120 000 1973 Mechanical draft . Mátra (Gagarin) Power Station. Mátra (Gagarin) Power Station. Bilibino Nuclear Power Station. Armenia 210 580 000 1970 Natural draft steel tower with louvres 11. Hungary 220 580 000 1972 Natural draft. with louvres 8.Ref. Iran 210 740 000 1984 Steel tower with louvres and deluged peak coolers Page | 2 GEA EGI Contracting/Engineering Co. Razdan Power Station. Hungary 100 290 000 1970 Natural draft. Armenia 210 580 000 1971 Natural draft steel tower with louvres 12. Russia 12 120 000 1973 Mechanical draft . Unit No. with louvres and DC heater 9.egi. Unit III. Eilenburg Chemical Works Germany Karaganda Steel Mill. Description Country Turbine Cooler CommisRemark Power surface sioning (MW) (m²) ________________________________________________________________________________________________________ 1. Unit V. Razdan Power Station. No. Hungary 220 580 000 1972 Natural draft.3 26 000 1964 Mechanical draft Kazakhstan 6 40 000 1968 Mechanical draft. Unit I. Mátra (Gagarin) Power Station Hungary — 9 600 1981 LOTHUS system. preheating. Bilibino Nuclear Power Station Unit I. Unit VI. Trakya Power Station. Unit II. Great Isfahan Power Station. Budapest. Iran 210 740 000 1985 Iran 210 740 000 1985 28. Unit B. with louvres and deluged peak coolers 35.Ref. Description Country Turbine Cooler CommisRemark Power surface sioning (MW) (m²) ________________________________________________________________________________________________________ 26. Iran 210 740 000 1986 Steel tower with louvres and deluged peak coolers 29. Iran 250 840 000 1994 Natural draft steel tower. see Nos 30 and 31 40. Hungary www. Turkey 100 580 000 1988 Repeat order. with louvres and deluged peak coolers 37. Unit I. Datong Power Station. China 210 680 000 1987 Natural draft concrete tower with preheating system. No. Unit IV. Shahid Rajai Power Station. Turkey 100 580 000 1986 One tower for two units deluged peak coolers 31. Unit III. Trakya Power Station. Unit A. China 210 616 000 1993 Built by the Chinese licensee 43. Solar Power Station Ukraine 5 11 300 1986 Mechanilcal draft tower with surface condenser 30. Teshrin Power Station. Unit IV. Turkey 100 580 000 1987 One tower for two units deluged peak coolers 32. Fengzhen Power Station. Syria 210 710 000 1993 Natural draft steel tower. Unit III. China 210 616 000 1994 Built by the Chinese licensee 44. Unit IV. Unit I. three condensers per unit 33. Ltd. Great Isfahan Power Station. Turkey 100 580 000 1988 As above. Shahid Rajai Power Station. Datong Power Station. Unit V. with louvres and deluged peak coolers 41.hu . Unit III. Unit II. Trakya Power Station. with louvres and deluged peak coolers 42. Great Isfahan Power Station Extension. with louvres and deluged peak coolers 38. Trakya Power Station. China 210 680 000 1988 Natural draft concrete tower with preheating system. Unit C. with louvres and deluged peak coolers 36 Shahid Rajai Power Station. Iran 250 840 000 1993 Natural draft steel tower. Iran 850 000 1995 Natural draft concrete tower with louvres 27. three condensers per unit 34. Fengzhen Power Station. Shahid Rajai Power Station. Teshrin Power Station. Page | 3 15. Syria 210 710 000 1993 Natural draft steel tower. Unit D. see Nos 30 and 31 39.egi. Unit II. Iran 250 840 000 1993 Natural draft steel tower. Great Isfahan Power Station. Unit V. Iran 250 840 000 1992 Natural draft steel tower. Privodino Compressor Station Russia 82 000 1995 Mechanical draft with louvres 45.8 210 Steel tower with louvres and deluged peak coolers Steel tower with louvres and deluged peak coolers GEA EGI Contracting/Engineering Co. Great Isfahan Power Station Extension. Fengzhen Power Station. Montazer Ghaem Unit III. built by others 64. Great Isfahan Power Station Extension. Unit V. built by others 61. Syria 220 780 000 2001 Natural draft steel tower for 220 MW Page | 4 GEA EGI Contracting/Engineering Co. Iran 105 560 000 1999 Natural draft concrete tower for 320 MW CCPP designed by EGI. Unit VI. Arak Power Station Unit II. Iran 105 560 000 2000 Natural draft concrete tower for 320 MW CCPP designed by EGI. Armenia 300 795 000 1999 Natural draft steel tower for 2x300=600 MW with deluged peak coolers 55. built by others 60. built by others 65. Fengzhen Power Station. 62 000m² 51. Ltd. Bursa Power Station Unit A. Hungary www. Iran 325 1 030 000 2000 Natural draft concrete towers with louvres designed by EGI. Unit VI. Montazer Ghaem Unit II. Arak Power Station Unit I. Kanegafuchi Chemical Works Japan 60 110 000 1998 T60 heat exhangers. Iran 105 560 000 2001 Natural draft concrete tower for 320 MW CCPP designed by EGI. Iran 210 850 000 1998 Natural draft concrete tower 53.egi. built by others 59. built by others 62.Ref. Arak Power Station Unit III. Iran 325 1 030 000 1999 Natural draft concrete towers with louvres designed by EGI. Bursa Power Station Unit B. built by others 63.hu . China 210 674 000 1996 Built by the Chinese licensee 48. Montazer Ghaem Unit I. China 210 674 000 1995 Built by the Chinese licensee 47. Iran 210 850 000 1997 Natural draft concrete tower 50. Turkey 240 1 100 000 1999 Natural draft concrete tower for 700 MW CCPP with louvres and deluged peak coolers 57. No. Turkey 240 1 100 000 1999 Natural draft concrete tower for 700 MW CCPP with louvres and deluged peak coolers 58. Unit VIII. Armenia 300 795 000 2000 Natural draft steel tower for 2x300=600 MW with deluged peak coolers 56. Iran 210 850 000 1999 Natural draft concrete tower 54. Mátra Power Station Hungary 220 230 000 1998 Retrofitting 52. Al-Zara Power Station Unit I. Razdan Power Station Unit V. Razdan Power Station Unit VI. Iran 325 1 030 000 2001 Natural draft concrete towers with louvres designed by EGI. Great Isfahan Power Station Extension. Arak Power Station Unit IV. Description Country Turbine Cooler CommisRemark Power surface sioning (MW) (m²) ________________________________________________________________________________________________________ 46. Budapest. Unit VII. Iran 325 1 030 000 1999 Natural draft concrete towers with louvres designed by EGI. Tereshkovo 340 MWe CHP PS Russia 70 721 800 2010 Induced draft steel tower with TA-67 fins.Ref. Unit 8 China 600 1 600 000 2007 Natural draft concrete tower shell.hu . Description Country Turbine Cooler CommisRemark Power surface sioning (MW) (m²) ________________________________________________________________________________________________________ 66.egi. Phase II. Al-Zara Power Station Unit III. Sochi 72 MWe CHP Unit 1. Gebze 770 MWe CCPP Unit I. winterization louvers and surface condensers Page | 5 70 GEA EGI Contracting/Engineering Co. Yangcheng. Al Nasserieh 510 MWe CCPP Syria 160 907 000 2008 Natural draft steel tower for 160 MW with DC Jet Condenser 78. Kojuhovo 340 MWe CHP PS Russia 721 800 2010 Induced draft steel tower with TA-67 fins. winterization louvers and surface condensers 77. Budapest. with louwers 75. Modugno 800 MWe CCPP Italy 300 921 600 2009 Low noise induced draft steel tower with DC Jet Condenser 80. CAN 2 x 160 MW CFB based Thermal Power Station Turkey 160 992 000 2004 Natural draft single concrete tower shell for 2 units. Turkey 270 1 100 000 2002 Natural draft concrete tower for 770 MW CCPP with louvres 70. Yangcheng. Syria 220 780 000 2001 Natural draft steel tower for 220 MW 68. Moscow City 130 MWe CCPP Russia 46 110 400 2008 Forced draft steel tower with TA-67 fins. Turkey 270 1 100 000 2002 Natural draft concrete tower for 770 MW CCPP with louvres 72. Syria 220 780 000 2001 Natural draft steel tower for 220 MW 67. Al-Zara Power Station Unit II. Russia 24 110 000 2004 Induced draft steel tower with prehumidification system 74. with louvres and deluged peak coolers 73. Deir Ali 750 MWe CCPP Syria 220 1 157 200 2009 Natural draft steel tower with DC Jet Condenser 81. Adapazari 770 MWe CCPP Unit I. Phase II. No. Ltd. Újpest 100 MWe CCPP Hungary 36 55 300 2001 Forced mechanical draft dry/ deluged stand-by and auxiliary cooling tower 69. Turkey 270 1 100 000 2002 Natural draft concrete tower for 770 MW CCPP with louvres 71. winterization louvers and surface condensers 82. Hungary www. with louwers 76. Zayzoun 510 MWe CCPP Syria 160 907 000 2008 Natural draft steel tower for 160 MW with DC Jet Condenser 79. Unit 7 China 600 1 600 000 2007 Natural draft concrete tower shell. Gebze 770 MWe CCPP Unit II. 6 winter. Unit 5. Unit 2. China 660 1 600 000 2010 Natural draft concrete cooling towers with louvers and surface condensers 94. Pervomaysk 180 MWe PP Unit 2. Strogino I. Unit 6. Petersburg . Unit 1. Pervomaysk 180 MWe PP Unit 1. Shuidonggou 660 MWe. Strogino II. Russia 66 328 000 2010 Supply of Heller dry cooling system of special outfit to the extension of Pervomaysk District Heating Plant No. BaoJi 660 MWe SC PP. Shanyin 2x300 MWe PP China 300 1 600 000 2011 Single natural draft concrete cooling tower for 2 units with louvers. FGD in tower.cell rows 89.cell rows 90. Russia 24 110 000 2009 Induced draft steel tower with prehumidification system 91. 88. Szakoly 20 MWe Biomass Power Plant Hungary 20 77 800 2009 Low noise induced draft steel tower with DC Jet Condenser 84.Ref. No. Russia 66 328 000 2010 Supply of Heller dry cooling system of special outfit to the extension of Pervomaysk District Heating Plant No. 14 of St. 2 summer fan . winterized 86. China 660 1 600 000 2010 Natural draft concrete cooling towers with louvers and surface condensers 93. FGD in tower. 92 Shuidonggou 660 MWe. DC jet condensers also serving the boiler feed pump turbines. China 660 1 670 000 2010 Natural draft concrete cooling towers with louvers. Description Country Turbine Cooler CommisRemark Power surface sioning (MW) (m²) ________________________________________________________________________________________________________ 83.6 winter. 87.egi. Sochi 72 MWe CHP Unit 3. Russia 42 230 400 2009 Induced draft steel tower. Russia 42 230 400 2009 Induced draft steel tower. Petersburg . 14 of St. 2 summer fan . winterized Page | 6 GEA EGI Contracting/Engineering Co. winterized 85. Ltd. Hungary www. China 660 1 670 000 2010 Natural draft concrete cooling towers with louvers.hu . FGD in tower. BaoJi 660 MWe SC PP. DC jet condensers also serving the boiler feed pump turbines. Novy Urengoy 120 MWe CCPP Russia 40 389 000 2011 Induced draft steel tower. Budapest. DC jet condensers also serving the boiler feed pump turbines.