First 70-632 Exam Test (Mai 2009)

May 28, 2018 | Author: kengneherve3732 | Category: Technology, Computing, Software, Computing And Information Technology, Business


Comments



Description

TEST DE PREPARATION A L’EXAMEN 70-6321. You create a large project plan in Microsoft Office Project Standard 2007. Immediately before an important status meeting, the project sponsor requests that you display the Work Breakdown Structure (WBS) numbers. You have not customized the WBS code. You need to display the WBS numbers as quickly as possible. What should you do? o A. Enter the WBS numbers as part of the task names. Even we have entered WBS number, we would need to get to the “show outline number” check box in option dialog to display the WBS numbers The only way this can be done is through the option dialog box o B. Change project options to show the outline number. o C. Refer to the ID field in a task table that you are using. WBS displaying can not be obtained through this way 2. You are creating a project management methodology. You document project management procedures and create specialized project management process templates. You need to apply the processes in the context of Microsoft Office Project Standard 2007. What should you do first? The ID field is just concerned with the id of tasks in Gantt view. It doesn‟t show the subtasks structure as the WBS does. o D. Insert the Unique ID field in a task table that you are using. o A. Create a Project Guide. o B. Display the Task Drivers pane. Not useful Project is like a wizard used to lead us through the major phases of the project Displaying this item will only give us information on an activity o C. Display the Hyperlinks column. o D. Display the Microsoft Office Online Web site. 3. You are using a project plan created by another person as an example of how to create a project in Microsoft Office Project Standard 2007. However, you do not want the original authors name to be associated with your project plan. You need to remove the original project plan author's name from the project plan. What should you do? o A. Increase the macro security level to High. o B. Delete the user name from the program options. It seems le option “program options” doesn‟t exist Macro security is just concerned with macro execution o C. Remove the authors resource from the resource pool. By clicking on the file menu and properties o D. Turn on the removal of information from the file properties. the resource pool is not necessarily concerned with the file author‟s name 4. You are managing a project schedule in Microsoft Office Project Standard 2007. You create 100 new tasks in the project plan. Each task has a duration of 5 days, which you indicate by entering 5 in the What should you do? o A. Create a new project plan based on a template that does not have estimated durations. o D. Need to be understood o C. You need to change the calendar options to set the default amount of work to 8 hours. The project has a baseline and all values have been calculated. Set the default start time to 8:00 A. Also works . You need to stop the message from appearing. Change the width of the Duration column so the question mark is not visible. o B. Project displays a message about an alternative method of setting the task duration. The default task duration is 1 day. Enter standard resource rates that are greater than zero. o C. The actual cost of work performed (ACWP) for all tasks is $0.00. Each task has an estimated duration. It doesn‟t affect this dialog box So every time I will type same value for several cells. In the general program options. disable the feature that provides advice about scheduling.) o A. disable the feature that provides advice about using Project. calendar tab o B. You measure the performance of a project you are tracking in Microsoft Office Project Standard 2007 by updating the completion percentage of the tasks. This is done through the dialog box option. Are we on a 7 or 5 days basis? We can‟t select this option because the 40 hours could be set for 7 days Even we have set this option to 20. Set the days per month to 20.M. and assign a resource to the task. Turn off the Project Guide. and the default amount of work is 7 hours. you create a new task in a project plan. This is the only way we can do it through the option dialog box o C. and then perform a calculation. In the general program options. 6. You are entering tasks in a project plan in Microsoft Office Project Standard 2007. Doing that will only affect information display in the column This is a check box „‟estimated‟‟ in the information dialog box o C. In Microsoft Office Project Standard 2007. dialog box won‟t be shown again o B. What should you do? o A.00. Set the hours per week to 40.M. Choose two. o D. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. After every third task you create. Select the Physical % complete option for earned value purposes.Duration field. and the default end time to 4:00 P. 7. select the Don‟t tell me about this again check box. Disable the option to show that tasks have estimated durations. o D. In the message box. Anything doesn‟t tell us there 8 hour in a day Doing that will establish a constraint. Reenter the same durations so the question marks representing the estimates disappear. You need to make sure that no task in this project plan has a question mark in its Duration field. 5. Assign budget resources to the project summary task. o D. o B. Set the hours per day to 8. You need to ensure that the ACWP shows data other than $0. What should you do first? o A. Select the Manual calculation mode. Flag the summary tasks as milestones. You are tracking a project in Microsoft Office Project Standard 2007. The duration box is disabled Flagging the summary task as milestones will only tell us when important date will be reached o C. 10. o D. We will easily compare target date with forecast. You learn that the resource's task can be performed only on certain days. Convert the summary tasks into milestones by setting the duration of each to 0. What should you do? . Set a deadline on the last subtask of each deliverable. The question is concerned about the late date. The end of Week 2. The end of Week 1. This column only contains late end date of task 1 o C. o D. You are managing a project schedule in Microsoft Office Project Standard 2007. 11. Change the resource calendar to match the task calendar. The calendar for one of your resources has been edited to block out his vacation days. and you create a calendar indicating those days. You need to be able to display all tasks of all projects by phase. The end of Week 3. 9. The project follows the plan shown below: What is the late finish of task 4? o A. not the early end date. Ensure that the earned value is calculated based on physical percentage of completion. it end date including lag time is in the week three column.8. What should you do? o A. We would have picked this answer otherwise. The project schedules you manage in Microsoft Office Project Standard 2007 all follow standard project lifecycle phases. What should you do? o A. You need to keep track of how close the forecast completion dates of these deliverables are to their target dates. The end of Week 4. Modify the resource calendar so that it will override the task calendar. o B. You need to set the calendars correctly for this resource assignments. o B. o D. Each is of these tasks is represented by a summary task and a series of linked subtasks. Although the bar representing the task is entirely in week 2 column. Assign the new calendar to the task. Create a vacation exception on the project calendar. The lag time extends the end late date of the task. o C. Project team members are working on several of the tasks in your Microsoft Office Project Standard 2007 schedule in parallel. o B. assign resources to summary tasks that represent phases. and then insert links to the new task. There is one starttostart dependency from Task A to Task B. You need to add a new task to one of the subprojects from within the consolidated project file. o B. 13. Use this plan template for all projects. Differentiate between cost items and work items by using a projectspecific prefix. o C. Use an Outline code with a mask for cost data. create a custom task text field with a value for each phase. tasks won‟t be shown and we couldn‟t insert task in the right place o B. Create a duplicate file that has the WBS set up according to cost code. and then insert the new task directly below it. In Microsoft Office Project Standard 2007. Expand the subproject. What should you do? o A. and then insert the new task. and an As Soon As Possible constraint on Task B. Subtract 2 days from the lag on the dependency. The project is organized using Work Breakdown Structure (WBS) codes. Select the project summary task of the subproject. o D. . It will delay the start date of 2 days This is not what has been asked This corresponds to a lag of 2 days. associate the resource pool with all projects. Within a master project that contains all projects. and then display all tasks. Change the dependency to finishtofinish with 2 days lag. Use the Cost Performance Index. Change the dependency to finishtostart with 2 days lag. Within a master project that contains all projects. Create a shared resource pool. create a summary task for each phase. You manage a project in Microsoft Office Project Standard 2007. associate all tasks with one of the values.o A. You are working on a schedule in Microsoft Office Project Standard 2007. you have a consolidated project that links to subprojects. We just need to add a lag of two days o C. What should you do? o A. 14. o D. o B. What should you do? o A. o C. o B. Insert the new task in the consolidated project. We can easily see the right place where to insert If the subproject is collapsed. Add 2 days to the lag on the dependency. You need to provide the accountant with a different code that will meet her needs. o C. and then insert the new task into the subproject. o D. and then group all tasks by this field. Your organization's accountant wants to be able to break down and group costs in a different manner. You need to make task B start two days later than it currently does. Collapse the subproject. Not good o D. and then display all tasks. 12. Create a project plan template with the standard project lifecycle phases as summary tasks. This is done in a second part 18. You are using Microsoft Office Project Professional 2007 to plan a project. start date. Create budget resources. The budget cost and actual work details. 16. The budget cost and work details. The budget cost and cost details. o D. 17. set the number of days of slack to less than or equal to 5 days for critical tasks. o B. o D. You will use the budget tracking feature to track the project costs against the budget. Then you display the project summary task. Save a project baseline. . Filter the project schedule to display only tasks with more than 5 days of free slack. In Microsoft Office Project Standard 2007. a delay of more than 5 days will impact the project end date. What should you include in a usage view? o A. you create the following project plan: You need to display the factors that influence the start date of task 4. By definition. What should you do? o A. lead and lag.15. What should you do? Set up budget resources first o A. you assign the budget to the project plan. Display the Task Usage view. Display the Earned Value Cost Indicators table. The project has a fixed budget. Display the Task Drivers pane. You need to set up your project plan so that you can start tracking the costs. The budget cost and actual cost details. o C. task drivers are factors that directly impact the execution of a task like constraint. Your project has a fixed resource budget. and you assign resources with a standard rate to the project tasks. o B. Assign cost resources to the project summary task. o D. A project that you are tracking in Microsoft Office Project Standard 2007 has tight deadlines that must be met. Display the Resource Usage view. o C. o B. In Microsoft Office Project Standard 2007. finish date. Filter the project schedule to display only tasks slipping by more than 5 days. You need to compare the budget cost with the project cost. o C. What should you do first? o A. Insert the Critical column into the Gantt Chart view. o B. In the calculation options. For some tasks. slack o C. You need to identify these tasks as critical. It will just affect the chart diagram. we want to see all task organized by WBS. o B. You need to set up the schedule so you can easily switch between viewing all tasks organized by WBS and by the month they are scheduled to end. it starting date doesn‟t have importance. scheduling from the start of the project. o B. You are preparing a multiyear project schedule in Microsoft Office Project Standard 2007. Insert both project plans into a third project plan.Create a visual report of each project plan. You need to display a single critical path across both projects in the Gantt Chart view. The dependency between Task Z and Task X. so it is directly the next activity X‟s starting date which is impacted. o D. You notice that Task X is starting later than you expected. X will start at the project beginning date. You need task X to start on Tuesday. The dependency between Task X and Task Y. 20. and then merge the data in Microsoft Office Excel 2007. o B. Because task W have been completed. we must define the month as interval. As preview 21. o D. o C . second. Because there won‟t be any relation between these both activities. What should you do? o A. o D. Not an interesting practice. The dependency between Task W and Task X. Create a custom filter based on the Date Range filter. You are editing a schedule in Microsoft Office Project Standard 2007. and then display them side by side. The dependency between Task A and the summary task. We have to display a single critical path provided by two project in a Gantt chart view . Then in the third project plan. In the group creation. Task W is 100 percent complete. You have two project plans in Microsoft Office Project Standard 2007 that are part of one large initiative. expand the inserted projects and all their tasks. X will start at the project beginning date. So we have to create a group based on finish date. if that relation is broken. We want to display a single critical path across. Define Group By criteria for finish dates. Open both project plans. we want to organize them in month. Set the project timescale to use months as the middletier interval. Display the Project Information dialog box. Which dependency do you delete? o A. with an interval of months. Set the project timescale to use months as the bottomtier interval. What should you do? This won‟t affect the task list. This answer will display critical path twice. 19. And it is based upon the relation between activity A and W. o C.o D. o A. Copy and paste the tasks of each project plan into a spreadsheet in Microsoft Office Excel 2007. X will start just after W Because there won‟t be any relation between these both activities. First. o C. What should you do? o A. You are managing a project schedule in Microsoft Office Project Standard 2007. The resource is assigned to a task that is currently in progress. Set a Must Start On constraint on January 5 and a Finish No Later Than constraint on January 8. Set a Must Start On constraint on January 5. Copy cost data from the Task Usage table into the accounting system. You need to schedule the task. You need to align the project schedule data with the cost accounts. Set a Start No Earlier Than constraint on January 5 and a Finish No Later Than constraint on January 8. o C. o C. Create a resource with the new rate and assign that resource to all tasks starting on or after the effective date of the cost increase. You are managing a project in Microsoft Office Project Standard 2007. Set a Finish No Later Than constraint on January 8. The cost of a resource has increased. You are adding a task to an existing project schedule in Microsoft Office Project Standard 2007. o D. It is not dynamically updated o B. 23. What should you do? o A. The task should start on not must start on o B. Enter budget resources. Enter cost resources. o D. You need to update your project budget so that Project will automatically calculate future costs without requiring manual adjustments. In the resources Cost table. January 8. 24. January 5 and must complete by Friday. The task should start Tuesday. C does. set the standard rate to increase on the effective date of the cost increase. What should you do? o A. This is the worst solution if we haven‟t a resource releasing policy Cost table obtained by double clicking on a task in the resource view .22. Your organization's accounting system utilizes cost accounts to track expenses against revenue. This is a valid constraint o D. Update the resources standard rate in the Resource Sheet. o B. Because A is false. Set up interim plans. o C. Update the resources Actual Cost in the Resource Usage view. o B. Create a custom basic report of resource work. Display the Resource Sheet and the Work table. We want to update the project with time worked per day. o C. In Microsoft Office Project Standard 2007. You need to create a dynamic. Complete field for the project summary task in the task Work table. and then copy all the table fields into a Microsoft Office Excel workbook. graphical representation of all resource work. o B. 27. The Physical % Comp. not the work task. o C. Enter Work in a task view. Set the status date to the current date. field for the project summary task in the task Tracking table. o B. So. What should you do? I don’t really understand progress line principle o A. Group the tasks by completion status. and then display a progress line. and then open the Project Statistics dialog box. 28. Sort the tasks by start date. You are tracking a project in Microsoft Office Project Standard 2007. In the Gantt Chart view. You are preparing for a presentation about a project that you are tracking in Microsoft Office Project Standard 2007. with a flexible timescale. In fact. o D. You need to update the project with time worked per day. You are tracking a project in Microsoft Office Project Standard 2007. Create a visual report of resource work. The % Complete field for the project summary task in the task Tracking table. o D. it doesn‟t give us information on actual work performed This is obtained through the tracking tab in the assignment information dialog box o C.25. Enter Actual Start in an assignment view. The % Work Complete field in the Project Statistics dialog box. Entering actual start will not update the project with time worked per day. Set the status date to the current date. 26. o D. you need to identify which tasks are behind schedule. What should you do? o A. Enter Actual Work in an assignment view. Enter Physical % Complete in a task view. this answer is incorrect o B. . The % W. You need to display the current status of the project. o C. and then copy a picture of them into a Microsoft Office PowerPoint presentation. you are tracking a project by duration. o D. Display the Resource Sheet and the Work table. The Updating task status updates resource status option is not activated. What should you display? o A. What should you do? o A. The first part of this answer is true. This is done after we have done the D answer o B. the resource has completed 5 days of work. Split the task. Set the current status date in the project information. Set the calculation option to Move end of completed parts after status date back to status date. shifting the remaining part of the task in the Gantt bar to start in 2 days. Start No Earlier Than and Must Start On Semi flexible and inflexible constraint . You are updating a project schedule in Microsoft Office Project Standard 2007. A critical task the resource is scheduled to start now conflicts with the completion of the current task. o B. so both task will not overlapping. Because the Gantt Chart is so large there is no room for the Project Guide task pane. with a lag of 5 days. We only have 2 ways to activate the project guide o C. You want to use the Project Guide task pane to help you initiate the project. o D. What should you do? o A. Set the calculation option to Move start of remaining parts before status date forward to status date. You assign one resource to a 5day task that is not on the critical path. o D.) o A. Add a finishtofinish link between the tasks. Project does not schedule work in the past. and reports that he needs another 2 days to complete the task. adjust the Work values to 0 for each of the next 5 30. Add a finishtostart link between the tasks. Of the following constraints. Select the Enable Display Project Guide check box on the Interface tab in the Options dialog box. As Soon As Possible and Start No Earlier Than This pairing contains both the most flexible o B. but the second part doesn‟t . How can you enable the Project Guide? (Choose all that apply. Set the progress lines at the status date. choose Turn On Project Guide. o D. Project Guide is not available. o C. o C. A task with one resource assigned to it was scheduled to be completed before the current status date.29. working days. You open Project to create a new project for your Company regarding event planning and execution. and 16 hours over the following 2 working days. which pairing contains both the most flexible and least flexible constraints? o A. However. o B. After 1 week. The A and B answer will not split the first task. Choose Turn On Project Guide from the View menu. What should you do? o A. Change the view from Gantt Chart to Calendar. when you rightclick the Standard toolbar. The initial action to do to display the project guide 32. The remaining portion of the work is still scheduled in the past. You need to delay the remaining work on the current task by 5 working days so the resource can complete the critical task first. with a lag of 5 days. In the timesheet portion of the Task Usage view. From the Insert menu. You update the % Complete field according to the status provided by the resource. You are planning a project in Microsoft Office Project Standard 2007. You need to ensure that when you update schedule information. 31. Decrease the macro security level. We can create a new calendar. Create a new calendar with the designated 40-hour work week and set the new calendar as the default calendar for all new projects by using the Options dialog box.M.5. You are working for Company com. But you do not want Mike’s name to be associated with your project plan. and then click Set As Default.) o A. So A is the best answer o C. with a one-hour lunch. He does not want to start a new project and have to input common tasks like reviewing tradeshow fees. How should you do? o A. It is false o D. The working hours for most of your resources are 8:30 A. We can also get template on the internet o D. to 8:30 A. John is in charge of putting together the company's presence at the 2008 electronics industry tradeshow. It's the first time his Company will be involved in a tradeshow. You enter 5 in the Duration field to set each task has 5 days duration.M. and determining payment options. The Standard calendar is applied by default and already contains the appropriate working times. and Wrap-Up. Doesn‟t interact with author name .o C. No change is necessary. Open the Options dialog box and change the start time from 8:00 A. but because most of our resources are starting at 8:30.M.. Which of the following can he use to get started? (Choose all that apply. o D. In the file properties. Because this template exists.M.M..M. You need to create 50 new tasks. Remove the Mike's name from the program options. it is not really necessary. You use a project plan created by Mike as a sample of how to create a project in Office Project Standard 2007. You are planning a project in Microsoft Office Project 2007. Execution. Which of the following options is a viable solution for defining these working times for all future tasks in which a start and finish date has not been defined as a default? o A. o B. turn on the removal of information option 36. o B. o C. As Soon As Possible and As Late As Possible Both are most flexible o D. Delete the Mike resource from the resource pool.5.5 and the hours per week to 37. This dialog box doesn‟t offer possibility to change working hour 34. we will redefine all the tasks 35. As Late As Possible and Must Start On 33. You are working for Company com. Use an existing tradeshow project on his company's server. to 5:00 P. obtaining sponsor approval. Use the Project Guide task pane to initiate the project and type the start date. Through this option. Use the Project template Tradeshow Planning. Open the Project Information dialog box and change the start time from 8:00 A. we can use it o C. and then click Set As Default. Access Microsoft Office Online and look for an appropriate template there. among other things. You manage a project schedule in Office Project Standard 2007. the hours per day to 7.5 and the hours per week to 37. o B. the hours per day to 7. to 8:30 A. M. Change the days per month to 20. choose Project Information. o B. The default amount of work is 7 hours. How to change the calendar options to set the default amount of work to 8 hours? o A. and from the New Project task pane. 40. There is not a feature that provides advice about scheduling in the general program options o D. Enter standard resource rates < zero. click Blank Project. o C. o D.You receive a message about an alternative method of setting the task duration every third task you create. The actual cost of work performed (ACWP) for all tasks is $0. you create a new task and assign a resource to it. On the Project Guide toolbar. Click File. choose New. Select the Physical % Complete option for earned value purposes. What are two possible actions to prevent the message from showing again? (Choose two) o A. Change the default start time to 8:00 A. o D. Disable the feature that provides advice about scheduling in the general program options. resource. What should you do first to ensure that the ACWP shows data other than $0.00. Create a new Project Guide. Your boss suggests you use the Project template named "Internal Readiness Training. select the template to use. click Resources. Click the Project Templates tab and select Internal Readiness Training. 39. Change the hours per day to 8. We want to change to 8 not to 7 o B. o C. choose New.00? The system is already configured with 20 days per month o A. In Office Project Standard 2007. In the Project Information dialog box. click On Computer Click the Project Templates tab and select the Internal Readiness Training template. The project has a baseline and all values have been calculated. o B. Which would you select to create a new project with total control so that you can enter every task. and the default end time to 4:00 P. You are working for Company com." How do you access this template? o A. and from the New Project task pane. Disable the feature that provides advice about using Project in the general program options. and from the Project Guide task pane. and assignment yourself? . Import the Internal Readiness Training template. o C. Enter standard resource rates > zero. Template. Choose Don't tell me about this again in the message box.M. Change the hours per day to 7. From the Project menu. Click File. Select the Manual calculation mode. o B. You track the performance of a project by updating the completion percentage of the tasks. You are in charge of setting up a project for internal readiness training for getting employees trained on using the new phone system you plan to install in three weeks. 37. You are working for Company com. and then perform a calculation. click Specify o C. o D. 38. A blank project . A template from Office Online o B. Any project under the Project Templates tab in the Templates dialog box o D. An existing project o C.o A. o B. Modify the summary tasks into milestones. you do not get the desired results. Turn off the Project Guide task pane. Format the Timescale as Days. You are working for Company com. You need to print a network diagram of your entire project. o B.. 43. select the dates you want to print in the o B. What do you do? o A. Before printing the document. Adjust the zoom level of the displayed Gantt Chart to display the date range you want to print all in your window. Timescale options in the Print dialog box. Disable the option to show that tasks have estimated durations. Modify the print settings in the Print dialog box. Use the printer's advanced properties to select Landscape view. o C. Re-enter the same durations so the question marks representing the estimates disappear. Configure a deadline on the last subtask of each deliverable. How can you solve this problem? o A. o D. Your team members are working on three tasks in your Office Project Standard 2007 schedule at the same time. each time you print the Gantt Chart. o B. Enable the option to show that tasks have estimated durations. You want the chart to fit on one page. o D. o C.How make sure that no task in this project plan has a "?" in its Duration field? o A. However. . Use the printer's advanced properties to select Landscape view. 44.You create tasks in a project plan. Use the printer's advanced properties to select Landscape view. How to track how close the forecast completion dates of these deliverables are to their target dates? o A. Create a new project plan based on a template that does not have estimated durations. in Land scape view. Each task has an estimated duration. Before printing the document. Ensure earned value is calculated by physical percentage of completion. and with the results only from the last month showing. Modify the zoom level on the Network Diagram to match the size at which the diagram will print. o D. Unfortunately. Before printing the document. Each task is represented by a summary task and some related subtasks.41. o C. o C. Modify the Network Diagram legend in the Project Information dialog box. and then print with the Print dialog box defaults. o D. Project's Print feature will make the Gantt Chart fit on the printed page by default. Print the document using Landscape view using your printer's properties page. You need to print a Gantt Chart to show your boss how much you've achieved over the last month in relation to your project's timeline. Format the Timescale as Years. select the dates in the Timescale options in the Print dialog box. Indicate the summary tasks as milestones. Format the Timescale as Months. select the dates in the Timescale options in the Print dialog box. You are working for Company com. 42. each time you click Print and accept the default settings from the Print dialog box. the data you want to print doesn't print on a single page. You are working for Company com.You manage project schedules in Office Project Standard 2007. which follow standard project lifecycle phases. o D. o B. 46. o B. Instruct her to use an Outline code with a mask for cost data. o B. 48. How can you accomplish this? o A. Use the plan template with the standard project lifecycle phases as summary tasks for all projects. Create the task in the Entry table and set the Duration field to seven days.45. o C. Right-click the timescale displayed above the chart and choose Change Working Time from the shortcut menu. Options and click the Schedule tab. o C. You need to create a new task with a duration of seven days. You are managing a project using Microsoft Office Project 2007. How to provide the accountant with a different code that will meet her requirement? o A. Change Working Time from the menu o C. You are working for Company com. You manage a project organized by WBS codes in Office Project Standard 2007. Set the duration to seven days. Your accountant wants to break down and group costs in a different manner. . create a custom task text field with a value for each phase. and then display all tasks. 47. Choose Tools. Your current project file is configured to use the Standard calendar. you are viewing the Gantt Chart and would like to customize the color of the non-working time indicators.How to display all tasks of all projects by phase? o A. o D. o D. Differentiate between cost items and work items by using a project-specific prefix. In a master project including all projects. Create a summary task for each phase. o C. and then group all tasks by this field. Choose Tools. Create the task in the Entry Table and set the duration to one week. associate all tasks with one of the values. Create the task in the Entry Table and set the Duration field to one week. Assign resources to summary tasks that represent phases. Instruct her to use the Cost Performance Index. Double-click the timescale displayed above the chart and click the Non-Working Time tab o D. What is the correct way to input the task and set the duration to seven days? o A. and then display all tasks. Currently. Create the task in the Gantt Chart by right-clicking and selecting New Task. o B. Instruct her to create a duplicate file that has the WBS set up according to cost code. Of the following options. In the Project Information dialog box. Create a project summary task and assign a task start date of October 15. assign a project start date of October 15. Resource management o D. assign a project start date of October 15. 50. Top-down method o C. o D. You are planning a project using Microsoft Office Project 2007. Bottom-up method o B. Create a task entitled "Project Start" and assign a task start date of October 15.49. Resource planning . You began planning this project four weeks ago and the first task is scheduled to begin in a few weeks on October 15. Which term describes estimating the cost of your project based upon the resources you will be using? o A. o B. which is the best practice for setting the date on which the project is scheduled to begin? o A. o C. In the Properties dialog box. REPONSES AUX QUESTIONS Q 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 A B A D B. D A B B D B D B A D B C C C D . D D A B. C D B. D A B A A B C D B B A D A B B A B D B B C C Q 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 A C A C D D A.
Copyright © 2024 DOKUMEN.SITE Inc.