ULT CORPORATION PTE LTD7E PIONEER SECTOR 1 SINGAPORE 628446 TEL: 64153078 FAX: 68631928 ER420-NEW ROAD LINK BETWEEN UPPER CHANGI ROAD AND UPPER CHANGI ROAD EAST METHOD STATEMENT Bakau piling for 1500 RCU Drain along MC02 PREPARED BY APPROVED BY SAFETY OFFICER DATE OF SUBMISSION REVISION : HARIRAM MANOHARAN : GOO KIANG TIONG, JIMMY : LEE SHANG KENG : :0 ER420_MS of Bakau Piling works for 1500 RCU_r0.doc TABLE OF CONTENTS: 1. Objective 2. Project Overview 3. Resources: Plant and Manpower 3.1. Hierarchy Chart for this Operation 3.2 Relevant certificates for manpower and Equipment 4. Method Statement 4.1. Service/ Utilities in the Vicinity of work 4.1.1. List of services 4.1.2. Protective Measures 4.2 Schedule of Works 5. Emergency Plan 5.1 Evacuation Plan 5.2 Damage to services 5.3 Lists of essential Personnel 6. Safety and Environmental 6.1 Lists of personal protective equipment (PPE) 6.2 Permit to Work System 6.3 Risks Assessment and hazard Analysis Appendix 1- Location Plan of Proposed Bakau piling works Appendix 2- Relevant Certificates for Manpower & Equipment Appendix 3-Services/Utilities in the Vicinity of Work Appendix 4- Permit to Work Forms Appendix 5- Risk Assessment and Hazard Analysis ER420_MS of Bakau Piling works for 1500 RCU_r0.doc doc . 2) PROJECT OVERVIEW:The works under contract ER420: New road link between Upper Changi Road and Upper Changi Road East mainly comprises of the following: Construction of new road between Upper Changi Road and Upper Changi Road East Construction of New junctions in the Upper Changi Road and Upper Changi Road East Construction of Rigid Pavements at the junctions Widening a Part of Upper Changi Road Milling and Patching works in Upper Changi Road and Upper Changi Road East Construction of Drains.No Machinery: 1 Excavator fitted with 3 meter long steel dolly( Excavator with valid LM certificate) Manpower: Site Engineer Surveyor Site Supervisor Safety Supervisor Banksman General Worker 1 Item Qty 3 4 5 6 7 7 1 1 1 1 1 7 ER420_MS of Bakau Piling works for 1500 RCU_r0. Box culverts and sumps Construction of Two Bus Bays and Bus Shelter Slabs Installation of railings 3) RESOURCES:PLANT & MANPOWER:Sl.1) OBJECTIVE:The purpose of this document is to describe the methodology for the Installation of Bakau piles for 1500 RCU drain works along Upper Changi road MC02. Updated relevant certificates will be submitted before the commencement of work.3.2) RELEVANT CERTIFICATES FOR MANPOWER AND EQUIPMENT:- The relevant certificates for Manpower and Equipment are attached in Appendix 2.doc . ER420_MS of Bakau Piling works for 1500 RCU_r0.1) HIERARCHY CHART FOR THE OPERATION:- Project Manager Site Engineer Safety Supervisor Site Supervisor Surveyor Excavator operator Foreman Banksman General Worker 3. Start the installation of Bakau piles.doc .1) SERVICES/UTILITIES IN THE VICINITY OF WORK:- 4. 4. The depth of excavation is 2. 3) When the excavation reaches the required depth. Care is to be taken that no unsafe acts are carried out near the AC main. 5) The length of the metal dolly is 3m. Trial trenches were done before the sheet piling works to ensure the absence of any services within the work area.1. The workers are then to move away from the pile. 2) Excavate the trenches to the required depth for the laying of precast RC U-drain. Regular checks are to be carried out to look for any possible leakage in the 500 AC Main.2) Protective measures: Even though there are no services running exactly below the piling area.1) List of services: There are no services running along the work area.1. The sheet piling works have been completed already. 4.5 meter from the bakau piling area. 6) The work sequence is.2.2) SEQUENCE OF BAKAU PILING WORKS: 1) Set out the proposed 1500RCU drain alignment as per setting-out plan. If necessary.5m which means that the entire excavator bucket will be above the strut area when the bakau piles are completely installed. there is a 500mm AC Main at a distance of 7. 4) Bakau piles are installed with the help of the Steel Dolly attached to the teeth of the excavator bucket. The dolly attached to the excavator bucket is then lowered and the bakau pile is inserted into the hollow part of the metal dolly. ER420_MS of Bakau Piling works for 1500 RCU_r0. The bakau pile is placed in the required location and is pressed into the soil by the workers up to possible depth.4) METHOD STATEMENT:4. worker will assist in inserting the pile in to the dolly. The dolly is then lifted up with much care to prevent it from hitting the workers near the work area.doc . The metal dolly is the pressed down gradually until the whole length of the bakau pile is inserted into the ground. Excavator Bucket 3m Metal Dolly 300mm Bakau Pile ER420_MS of Bakau Piling works for 1500 RCU_r0. The next bakau pile is placed 300mm from the previous pile and the same process is continued. Struts 2.doc .5m 1900mm 1500mm RCU Drain 50mm Thick lean concrete 3.5m x 75mm Bakau pile Sheet Pile 300mm 300mm 300mm 300mm 300mm 300mm ER420_MS of Bakau Piling works for 1500 RCU_r0. e. 6) Where excavators are used. 4) All workers shall wear Personal Protective Equipment e. ER420_MS of Bakau Piling works for 1500 RCU_r0. 2) Proper barricade and signage shall be provided to warn the workers to divert away from deep excavation 3) Work area must be cleaned and stagnant water cleared daily. the emergency evacuation plan is as follows: Site work in the vicinity will be stopped The reporting of the occurrence of accident will go up the company hierarchy i. care shall be taken to ensure that no materials are stacked within the swinging area of the excavator.1) EVACUATION PLAN:Upon the occurrence of work site accident. reflective safety vest. 5) Site supervisor shall supervise throughout the entire piling works. and then the RTO and LTA will be informed Site and safety supervisors will be taking charge of securing the area Any hurt personnel will be carefully shifted to a secure location for first aid and subsequent evacuation to nearby hospital Unhurt work personnel will be gathered at a safe with headcount accounted for. supervision and traffic control in work areas.g. safety helmet within the site.doc . They will receive further instructions Accident area to be investigated and subsequently cleared. who will inform the project manager. workers inform supervisors/engineers. 5) EMERGENCY PLAN:5.SAFETY PRECAUTION 1) Work site shall be cordon off from public access. he is wholly in-charge of safety. 3) LIST OF ESSENTIAL PERSONNEL:Name Jimmy Goo Hariram Lee Shang Keng Soh Eng Soon Fong Heng Wong Solaiappan Subramanian Velayutham Muniyandi Designation Project Manager Site Engineer Safety Officer Site Supervisor Site Supervisor Site Supervisor Safety supervisor Contact number 9695 7413 9447 7749 9666 0582 9068 4578 8402 5141 8433 2276 8259 0048 6) SAFETY AND ENVIRONMENTAL:6. the follow up action is as follows: Site work in the vicinity will be stopped The reporting of the occurrence of accident will go up the hierarchy Site and safety supervisors will be taking charge of securing the area A report for services damage are be made immediately to the following hotline number.1) List of Personal Protective Equipment (PPE):S/No 1 2 3 4 5 6 Safety Helmet Safety boots Reflective vest Hand Gloves Full Body Harness( If applicable) Face Mask and Safety Goggles PPE ER420_MS of Bakau Piling works for 1500 RCU_r0.2) DAMAGE TO SERVICES:- In spite of all the precautionary measures taken. if there is any damage to the existing service.doc . PUB-1800-284 6600 SPPG-1800-778 8888 SINGTEL-1800-288 4099 5.5. doc . Refer to Appendix 6 for the relevant forms.3) Risk Assessment and Hazard Analysis:- Refer to Appendix 7 for the Risk assessment and Hazard analysis for the work. 6. ER420_MS of Bakau Piling works for 1500 RCU_r0.2) Permit to Work System:All relevant Permit to Work forms would be submitted before the operation.6. doc .APPENDIX 1 LOCATION PLAN FOR BAKAU PILING WORKS ER420_MS of Bakau Piling works for 1500 RCU_r0. ER420_MS of Bakau Piling works for 1500 RCU_r0.doc . APPENDIX 2 Relevant Certificates for Manpower and Equipment ER420_MS of Bakau Piling works for 1500 RCU_r0.doc . ER420_MS of Bakau Piling works for 1500 RCU_r0.doc . ER420_MS of Bakau Piling works for 1500 RCU_r0.doc . doc .ER420_MS of Bakau Piling works for 1500 RCU_r0. doc .ER420_MS of Bakau Piling works for 1500 RCU_r0. APPENDIX 3 Services/Utilities in the Vicinity of Work ER420_MS of Bakau Piling works for 1500 RCU_r0.doc . ER420_MS of Bakau Piling works for 1500 RCU_r0.doc . APPENDIX 4 Permit to Work.doc .Forms ER420_MS of Bakau Piling works for 1500 RCU_r0. APPENDIX 5 Risk Assessment and Hazard Analysis ER420_MS of Bakau Piling works for 1500 RCU_r0.doc .
Report "ER420_MS of Bakau Piling Works for 1500 RCU_r0"